CASE STUDIES


              with    the   public   sector   (ESP). The ESP identifies  Pune (PMC) Case
              strengths of drawing service    and evaluates the energy        Pune Municipal Corporation
              standards/      specifications  saving   opportunities   and    (PMC) has undertaken  an
              and competitive procurement     recommends improvements         initiative towards achieving
              systems.                        that can be paid for through    energy efficiency through PPP
              PPPs can play an important      energy savings.  The ESP        for the city streetlight system
              role in achieving municipal     usually guarantees that the     currently operated by it. The
              energy efficiency through       savings will meet or exceed     PMC entered into a service
              retrofitting of current energy   annual payments that cover     contract under PPP with M/s
              systems with modern and         all project costs; in case of any   Tata Projects Ltd through
              efficient  energy    systems.   shortfall, the ESP will pay the   its  subsidiary  –  Ujjwal  Pune
              Given    the    not-so-capital  same. The contract clearly      Ltd. This project is first of its
              intensive nature of municipal   identifies  the   procedures    kind  taken up by the  PMC
              streetlight       retrofitting  by  which  these are to  be     under PPP mode, wherein
              projects,   various   service   measured  and verified. The     the  necessary  luminescence
              contracts are appropriate PPP   concern  about ESP’s ability    is to be maintained with
              model. Performance contracts    to meet future financial        no    additional    financial
              can be designed for all project   obligations  in the event     investments.  The project is
              sizes and scope through         of not achieving adequate       fully self-financed through
              tailoring  to   the   energy    net energy savings (after       energy          consumption
              conservation      programme     deducing project costs) can be   savings   and    reductions
              by   taking   advantage    of   addressed through a reserve     in     maintenance      costs
              energy saving opportunities                                     brought about by streetlight
              and the supply of products      fund     mechanism.     Such    retrofitting. Retrofitting of
              and services. Performance       reserve funds, also termed as   streetlight system involves
              contracting     in    energy    Escrow Funds, provide for       the replacement  of existing
              efficiency programme usually    meeting any funds shortfall.    incandescent/         photo-
              consists of three independent   Achieving            energy     luminescent       streetlamps
              agreements:                                                     with those that function on
                                              efficiency          through     Light Emitting  Diode (LED)
              (i)   Project   development     streetlight  retrofitting  in   technology. It also involves
                   agreement                  Indian cities                   replacement of street lamp

              (ii)  Energy service agreement  In this section, an attempt     posts as well as increasing
                                              is made to shed lights on       their number in order to
              (iii)  Financing agreement      the achievements of energy      achieve a better illumination
                                              efficiency in urban streetlight   through better placement (or,
              Performance       contracting   system by two large Indian      spacing) as well as improving
              is   a   common     way    to   cities – Pune and Hyderabad –   the monitoring  and control
              implement energy efficiency     by forging partnerships with    through automation.
              programmes and frequently       private  sector  in the form of
              covers the financing of needed   the PPP. The case analysis laid   3.1.1 Project snapshot
              equipment. It is an agreement   down below gives an account     Following  is  a  snapshot  of
              between      a     municipal    of the streetlight retrofitting   energy conservation achieved
              corporation    and    private   project snapshots and features   through streetlight retrofitting
              Energy    Service    Provider   in the two cities.              project in Pune.